Construction Look Ahead for 50 West 66th Street 10.9.18

Oct 9, 2018
Construction Look Ahead for 50 West 66th Street 10.9.18

Lendlease's project team for the 50 West 66th Street Construction Project has released updated details for "a look ahead" of construction activities that will occur the rest of this week and next week at the 50 West 66th Street site (aka 36 West 66th Street). Click here for a copy of the notice that can printed and posted in buildings.

Week of October 8, 2018

-      Support of Excavation and Rock Drilling within the site.

-      Earth Moving and Rock Removal.

-      Setting up scaffold for East wall

-      Waterproofing East wall

-      Saturday 10/13 continuation of non-noisy work only

Week of October 15, 2018

-      Support of Excavation and Rock Drilling within the site.

-      Earth Moving and Rock Removal.

-      Waterproofing East wall

-      Lathers mobilization at East wall

-      Concrete wall pour East wall

-      Saturday 10/20 continuation of non-noisy work only

For any questions about the project, Lendlease has an infoline that the public can contact: 36west66thst@lendlease.com or (212) 448-3995. 