Community Alerts

Construction Look Ahead for 50 West 66th Street 9.25.18

Sep 25, 2018
Construction Look Ahead for 50 West 66th Street 9.25.18

Lendlease's project team for the 50 West 66th Street Construction Project has released updated details for "a look ahead" of construction activities that will occur the rest of this week and over the next 2 weeks at the 50 West 66th Street site (aka 36 West 66th Street). Click here for a copy of the notice that can printed and posted in buildings.

Week of September 24, 2018

-       Support of Excavation and Rock Drilling within the site.

-       Earth Moving and Rock Removal.

-       Trucking Rock from the site.

-       Setting up scaffold for East wall

-       Waterproofing East wall

 

Week of October 1, 2018

-       Support of Excavation and Rock Drilling within the site.

-       Earth Moving and Rock Removal.

-       Trucking Rock from the site.

-       Setting up scaffold for East wall

-       Waterproofing East wall

-       Lathers mobilization at East wall

Week of October 8, 2018

-       Support of Excavation and Rock Drilling within the site.

-       Earth Moving and Rock Removal.

-       Trucking Rock from the site.

-       Waterproofing East wall

-       Concrete wall pour East wall

For any questions about the project, Lendlease has an infoline that the public can contact: 36west66thst@lendlease.com or (212) 448-3995. 

Photo credit: Binyan Studios