Lendlease's project team for the 50 West 66th Street Construction Project has released updated details for "a look ahead" of construction activities that will occur the rest of this week and next week at the 50 West 66th Street site (aka 36 West 66th Street). Click here for a copy of the notice that can printed and posted in buildings.

Week of October 22, 2018

-      Support of Excavation

-      Rock Drilling within the site and Rock chopping

-      Earth moving.

-      Scaffolding for foundation walls

-      Waterproofing

-      Rebar operations

-      Saturday work will include items above, but NO rock chopping or rock drilling.

Week of October 29, 2018

-      Support of Excavation

-      Rock Drilling within the site, Rock chopping and Rock removal.

-      Earth moving.

-      Scaffolding for foundation walls

-      Waterproofing

-      Rebar operations

-      Saturday work will include items above, but NO rock chopping or rock drilling.

For any questions about the project, Lendlease has an infoline that the public can contact: 36west66thst@lendlease.com or (212) 448-3995. 