District News
Construction Look Ahead for 50 West 66th Street Project 1.15.19
Jan 15, 2019Lendlease's project team for the 50 West 66th Street Construction Project has released updated details for "a look ahead" of construction activities that will occur the rest of this week and next week at the 50 West 66th Street site (aka 36 West 66th Street).
Week of January 14th, 2019
- Rock Drilling within the site, Rock chopping and Rock removal
- Rock pyrotechnics for elevator pits
- Earth moving and trucking
- Scaffolding for foundation walls
- Waterproofing
- Rebar and concrete operations
- 66th street, boom operation from street to remove temporary office
Week of January 21st, 2019
- Rock Drilling within the site, Rock chopping and Rock removal
- Earth moving and trucking
- Scaffolding for foundation walls
- Waterproofing
- Rebar and Concrete operations
For any questions about the project, Lendlease has an infoline that the public can contact: 36west66thst@lendlease.com or (212) 448-3995.
Photo credit: Binyan Studios