Lendlease's project team for the 50 West 66th Street Construction Project has released updated details for "a look ahead" of construction activities that will occur over two weeks at the 50 West 66th Street site (aka 36 West 66th Street).

Weekend of July 20th & 21st, 2019

  • Saturday & Sunday - 66th Street – Street utility work per DOT regulations

 

Week of July 22th, 2019

  • Material and equipment deliveries.
  • Formwork, rebar and concrete operations.
  • Sidewalk utility work on 65th street.

 

Weekend of July 27th & 28th, 2019

  • Saturday & Sunday - 66th Street – Street utility work per DOT regulations

 

Week of July 29th, 2019

  • Material and equipment deliveries.
  • Formwork, rebar and concrete operations.
  • Sidewalk utility work excavation on 65th street.

For any questions about the project, Lendlease has an infoline that the public can contact: 36west66thst@lendlease.com or (212) 448-3995. 