Lendlease's project team for the 50 West 66th Street Construction Project has released updated details for "a look ahead" of construction activities that will occur over two weeks at the 50 West 66th Street site (aka 36 West 66th Street).

Weekend of September  21st  & September 28th, 2019

  • Saturday & Sunday - 66th Street – Street utility work per DOT regulations

Week of September 23rd, 2019

  • Material and equipment deliveries
  • Formwork, rebar and concrete operations
  • Sidewalk utility work on 65th street

Week of September 30th, 2019

  • Material and equipment deliveries
  • Formwork, rebar and concrete operations
  • Sidewalk utility work on 65th street